Discussion brewed Thursday night regarding a plan that would pack LCF or Altadena streets with public works trucks hauling loads of dirt from Hahamongna Watershed Park.

Representatives of the L.A. County's Department of Public Works recommended at a public meeting Thursday night that dirt-hauling trucks cleaning out the Devil's Gate Dam travel over Windsor Avenue in Altadena - rather than using a side route in La Cañada – en route to the 210 Freeway.

The meeting was held Thursday to discuss possible routes in Altadena and La Cañada Flintridge, and though no decision has yet been made for the June dirt-hauling operation, DPW officials called the La Cañada side route "not viable," while suggesting that using Windsor would be the best alternative.

Residents of Windsor Avenue, La Canada Verdugo Road, Shelly Street and other neighborhoods came out to the meeting to voice their opposition to trucks in their neighborhood.

Find out what's happening in La Cañada Flintridgewith free, real-time updates from Patch.

's cafeteria was filled with voices offering input on a dam clean-out plan that could lead to public works trucks on the streets of Altadena and La Cañada. The meeting, hosted by Public Works, was designed to inform people of a quartet of possible routes for those trucks, along with some of the methodology behind those routes.

The plan is to haul 25,000 cubic yards of dirt out of the Hahamongna Watershed Park, which would lead to a force of about 40 to 50 trucks running up and down city streets for about three to four weeks in the summer, according to Steve Sheridan, an engineer for the Los Angeles County Flood Control District and the main presenter at the meeting. In a series of slides, Sheridan outlined that the trucks would be operating from Monday through Friday from 7:30 a.m. to 4 p.m.

Find out what's happening in La Cañada Flintridgewith free, real-time updates from Patch.

"We'd want to start the initial work in early June," he said. "And we'd like to start hauling after the Fourth of July weekend."

There were four alternatives presented. One would involve trucks traveling up through parking, then onto the streets starting at the intersection of Windsor and Ventura in Altadena.  The trucks would then travel up and down Windsor to the 210 Freeway. This was listed at the first alternative in Sheridan's presentation, which he said is the most "routinely used" and logistically seamless method available.

"There's no new construction, no impacts to the environment," he said. "The con, however, is that it's the longest route."

La Cañada was the focus of the second listed alternative, which featured a route that would go on to Oak Grove Drive to Berkshire Avenue and eventually the freeway, passing right by La Cañada High School. Sheridan said that while this offers the shortest, neighborhood-free route, it also involves the construction of an access road, moving vegetation, grading as well as trying to get permits for everything -- all of which couldn't be done in the allotted time frame.

Planning hurdles were also mentioned with the third alternative, which involves heading through even narrower residential streets on La Cañada Verdugo Road and Oak Grove Drive over to Windsor. Sheridan mentioned that along with congestion, parking, trash collection and other quality-of-life issues, the massive trucks used to haul the dirt simply aren't meant for skinnier residential roads.

Sheridan, however, touted the fourth alternative, with would temporarily treat the southernmost part of the basin as storage for most of the sediment until the much larger plan is implemented. The hauling project is a warm-up for a large-scale plan that could result in truck traffic on the same streets for years.

In the long term, Kerjon Lee, public affairs manager for L.A. County Flood Control, said they will need to remove roughly 2 million cubic yards of dirt from the dam over several years.

The full plan, which involves removing dozens of acres of mature black willow trees, require a full environmental impact report (EIR), a step county officials had originally hoped to bypass.  The County Board of Supervisors after local wildlife and open space advocates objected to the plan.

Sheridan said this fourth alternative is "the one we'd recommend," as it would also use even larger trucks to speed up the hauling process. Once the hauling starts, the trucks would use the same routes as indicated in the Windsor/210 alternative, Sheridan said.

But speed was not on the minds of many of the dozens of attendees at the meeting, who voiced plenty of concerns about any alternatives that would involve impacting residential areas.

"I think it's funny that the first alternative traces right through the middle of a residential area, and how that's not a key factor," said one attendee about the proposed Windsor-to-210 route. "Well, it's big for us, which is a reason you see a big turnout of people who live there."

Altadena Town Council Member Tecumseh Shackelford voiced his support for the second alternative, the one that passes by La Cañada High School and had been called not "viable" by Sheridan.

"That's the one we want, it keeps (the trucks) out of the neighborhoods. I know you said it's gonna take a little work, well, then you've got to put in a little work," Shackelford said, which drew applause and cheers from many in attendance. Hugh Bowles, a Shelly Street resident, asked people who wanted "Number 2" to raise their hands, and a majority of the crowd followed suit.

"Go get your permits!" he called out to Sheridan.

Bob Spencer, a spokesman for the Public Works department, has told Patch in the past that no ideal route exists.

"They've each got their benefits and their own downsides," Spencer said.

Edel Vizcarra, the planning deputy for Supervisor Michael Antonovich, La Cañada and Altadena's representative in the county, told Patch in a past story that a combination of the routes might be the best way to avoid the downsides of each one.

"In La Cañada you've got the Methodist Church and the high school, so you've got concerns over noise and traffic at certain times," Vizcarra said.  "In Altadena you have the issues that you're putting them on more residential streets that are narrow."

One possible plan would be for the trucks to run through La Cañada, when the church and schools are not in session, and through Altadena when they are, he said.

For more information on the projects, Sheridan pointed out a website (www.lasedimentmanagement.com) that will have the slides from this latest presentation up early next week. Readers can find past presentations and reports there as well.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.